YEOWARD CR FILL SLOPE RETAINING WALL

Services

  • Engineering & Construction

Customer

Tolko

Project Date

2010

Location

Shuswap

The objective of this project was to construct a GRS fill slope wall to allow a resource road to be constructed across a very steep sloped gully. Landmark provided the skilled labour and all small equipment required to complete this project. The project was completed in 6 days.

Project Details:

  • Construction Duration: 6 days
  • Structure Length (m): 45
  • Structure Height (m): 10
  • Foundation Material: Bedrock
  • Fill Material: Broken rock, sand, gravel
  • Finished Road Width (m): 10

Another successful project done in collaboration with Terratech Consulting Ltd.